Litigation and Dispute Resolution

Family trust feud: Gina Rinehart case and its implications

29 May, 2015

With a High Court appeal pending in the bank fees class action case, Paciocco v Australia and New Zealand Banking Group Limited [2015] FCAFC 50 (“Paciocco”), it is timely to undertake a review of where the law currently stands on penalties.

What is a penalty and what is the penalty doctrine?

In general terms, a stipulation prima facie imposes a penalty on party A if, as a matter of substance, it is collateral (or accessory) to a primary stipulation in favour of party B and this collateral stipulation, upon the failure of the primary stipulation, imposes upon party A an additional detriment, the penalty, to the benefit of party B: Andrews v Australia and New Zealand Banking Group Limited [2012] HCA 30 (Andrews).

In general terms, the penalty doctrine will be engaged, and render the penalty unenforceable by party B, where the penalty does not represent a “genuine pre-estimate” of the damage / loss that will actually flow to party B upon the failure of the primary stipulation.

This is a high bar, such that it has been said that for the penalty doctrine to be engaged the amount payable upon failure of the primary stipulation (the penalty generally is, but need not be the payment of money) must be “extravagant and unconscionable”: Andrews.  Or put another way, the penalty must be “out of all proportion” to the actual damage / loss likely to be suffered as a result of the breach: Ringrow Pty Ltd v BP Australia Pty Ltd (2005) 224 CLR 656.

Tips to bear in mind to avoid clauses being deemed a penalty

  1. Justify the damages clause on the basis that it is indeed a “genuine pre-estimate of loss”.
  • In order to avoid a clause being struck down as a penalty, it is advisable to explain and record the factors that have been taken into account in reaching the amount payable, with a view to showing that the damages are a genuine pre-estimate of loss. A wide range of factors may be relevant in this regard.
  • For example, in Paciocco v Australia and New Zealand Banking Group Limited [2015] FCAFC 50, the Full Court took into consideration the costs of increased regulatory capital, and the structural costs associated with ANZ running a collections department, to find that late payment fees charged by ANZ on consumer credit cards were not so exorbitant as to be classed a penalty. The Full Court commented that a broad range of costs incurred by the ANZ could be taken into account to assess whether the late payment fee was a penalty.
  • One option to achieve this in practice is to incorporate factors contributing to the pre-estimate of loss as a schedule / annexure to the contract. If this option is not suitable in the circumstances, it is advisable to keep a contemporaneous written record of how the amount / pre-estimate of loss was reached.
  • Furthermore, if the basis of the amount is difficult to quantify – it is helpful to say so. For example, the relevant clause (e.g. a liquidated damages clause) might say that because of the complexity of the subject matter of the contract, it is difficult for the parties to estimate the loss that will be suffered in the event of breach, and that the parties have therefore resolved to agree on a certain amount as representing the best estimate in all the circumstances.  This may help to avoid the clause being considered a penalty.
  • It is also advisable to expressly state in the contract that the parties acknowledge and agree damages payable on breach are a genuine pre-estimate of loss. Although courts will not necessarily place great weight on such statements (instead looking to the substance of the provision), they are likely to still be a relevant consideration.
  1. Don’t specify that the same penalty is payable on the occurrence of serious and trivial breaches. Put another way, it is advisable to link the severity of the breach to the amount payable.
  • Where the same amount is payable for triggering events of varying severity, it is difficult to maintain that the damages clause is a ‘genuine pre-estimate of loss’. It is therefore prudent to set a scale of damages payable according to the severity of the breach.  For example, in a contract for the supply of goods, where a minimum quantity is required to be ordered, you might have a scale of damages payable dependent on the quantity of goods that remain unordered.  You might also have reference to the time (e.g. days or weeks) that has passed to determine the amount payable.
  1. Don’t assume you’re safe from the laws of penalties simply because the damages clause isn’t triggered by a breach of contract
  • In Andrews, the High Court extended the type of clauses which may constitute penalties. The High Court held that a clause may constitute a penalty even when it is not triggered by a breach of contract. This altered the previous position where the law on penalties generally only applied to amounts payable on breach of contract.
  • This means that the law of penalties will capture a wider range of circumstances. In Andrews, the Court commented that certain bank fees (being the ‘honour’ and ‘dishonour’ fees, and overdraw fees) were capable of being characterised as penalties, even where the fees were payable in circumstances where no breach had occurred, and where customers had no obligation to avoid the occurrence of events triggering the fees (e.g. overdrawing an account).
  • This means that clauses with a punitive or penal character, where payment of a fee / damages is triggered upon certain conduct (even if that conduct does not constitute a breach of the agreement), may constitute a penalty, and be unenforceable. Since the decision of Andrews, even greater caution is necessary to avoid such clauses being considered a penalty.
  1. Rather than drafting damages being payable on breach, consider whether it is appropriate to utilise incentives based on positive conduct
  • This is particularly useful in the context of interest rates. It is common in loan agreements for a lender to charge a ‘default interest’ rate on breach of a repayment by the borrower, such that on default, the borrower is required to pay a higher interest rate. These provisions are at risk of constituting a penalty.
  • The general principle of penalties applies similarly here. A provision for the payment of interest at a higher rate after default is not a penalty “provided it can be seen as a genuine pre-estimate of compensation for loss the lender would suffer by being kept out of its money”: David Securities Pty Ltd v Commonwealth Bank of Australia (1990) 23 FCR 1 at 30 and 31.
  • However, if the agreement offers an incentive by reducing the interest rate following prompt payment, this is less likely to attract the rules on penalties (see, for example, Kellas-Sharpe and Ors v PSAL Limited (2012) Aust Contract Reports 90-377).

Concluding thoughts

It is important when drafting terms pursuant to which an amount is payable on breach (or on the undertaking of certain conduct), that special care is taken to avoid those terms being characterised as a penalty.  The above tips should be kept in mind when drafting any such clauses.

If you would like any assistance or further information in relation to liquidated damages clauses or clauses at risk of being considered a penalty, please do not hesitate to contact any of the below writers, who would be happy to assist.

Recent Insights

View all
Litigation and Dispute Resolution

Canadian Court elevates thumbs-up emoji to signature status

In June 2023, a Canadian Court in South-West Terminal Ltd v Achter Land and Cattle Ltd, 2023 SKKB 116, held that the "thumbs-up" emoji carried enough weight to constitute acceptance of contractual terms, analogous to that of a "signature", to establish a legally binding contract.   Facts This case involved a contractual dispute between two parties namely South-West Terminal ("SWT"), a grain and crop inputs company; and Achter Land & Cattle Ltd ("ALC"), a farming corporation. SWT sought to purchase several tonnes of flax at a price of $17 per bushel, and in March 2021, Mr Mickleborough, SWT's Farm Marketing Representative, sent a "blast" text message to several sellers indicating this intention. Following this text message, Mr Mickleborough spoke with Mr Achter, owner of ALC, whereby both parties verbally agreed by phone that ALC would supply 86 metric tonnes of flax to SWT at a price of $17 per bushel, in November 2021. After the phone call, Mr Mickleborough applied his ink signature to the contract, took a photo of it on his mobile phone and texted it to Mr Archter with the text message, "please confirm flax contract". Mr Archter responded by texting back a "thumbs-up" emoji, but ultimately did not deliver the 87 metric tonnes of flax as agreed.   Issues The parties did not dispute the facts, but rather, "disagreed as to whether there was a formal meeting of the minds" and intention to enter into a legally binding agreement. The primary issue that the Court was tasked with deciding was whether Mr Achter's use of the thumbs-up emoji carried the same weight as a signature to signify acceptance of the terms of the alleged contract. Mr Mickleborough put forward the argument that the emoji sent by Mr Achter conveyed acceptance of the terms of the agreement, however Mr Achter disagreed arguing that his use of the emoji was his way of confirming receipt of the text message. By way of affidavit, Mr Achter stated "I deny that he accepted the thumbs-up emoji as a digital signature of the incomplete contract"; and "I did not have time to review the Flax agreement and merely wanted to indicate that I did receive his text message." Consensus Ad Idem In deciding this issue, the Court needed to determine whether there had been a "formal meeting of the minds". At paragraph [18], Justice Keene considered the reasonable bystander test: " The court is to look at “how each party’s conduct would appear to a reasonable person in the position of the other party” (Aga at para 35). The test for agreement to a contract for legal purposes is whether the parties have indicated to the outside world, in the form of the objective reasonable bystander, their intention to contract and the terms of such contract (Aga at para 36). The question is not what the parties subjectively had in mind, but rather whether their conduct was such that a reasonable person would conclude that they had intended to be bound (Aga at para 37)."   Justice Keene considered several factors including: The nature of the business relationship, notably that Mr Achter had a long-standing business relationship with SWT going back to at least 2015 when Mr Mickleborough started with SWT; and   The consistency in the manner by which the parties conducted their business by way of verbal conversation either in person or over the phone to come to an agreement on price and volume of grain, which would be followed by Mr Mickleborough drafting a contract and sending it to Mr Achter. Mr Mickleborough stated, "I have done approximately fifteen to twenty contracts with Achter"; and   The fact that the parties had both clearly understood responses by Mr Achter such as "looks good", "ok" or "yup" to mean confirmation of the contract and "not a mere acknowledgment of the receipt of the contract" by Mr Achter.   Judgment At paragraph [36], Keene J said: "I am satisfied on the balance of probabilities that Chris okayed or approved the contract just like he had done before except this time he used a thumbs-up emoji. In my opinion, when considering all of the circumstances that meant approval of the flax contract and not simply that he had received the contract and was going to think about it. In my view a reasonable bystander knowing all of the background would come to the objective understanding that the parties had reached consensus ad item – a meeting of the minds – just like they had done on numerous other occasions." The court satisfied that the use of the thumbs-up emoji paralleled the prior abbreviated texts that the parties had used to confirm agreement ("looks good", "yup" and "ok"). This approach had become the established way the parties conducted their business relationship.   Significance of the Thumbs-Up Emoji Justice Keene acknowledged the significance of a thumbs-up emoji as something analogous to a signature at paragraph [63]: "This court readily acknowledges that a thumbs-up emoji is a non-traditional means to "sign" a document but nevertheless under these circumstances this was a valid way to convey the two purposes of a "signature" – to identify the signator… and… to convey Achter's acceptance of the flax contract." In support of this, Justice Keene cited the dictionary.com definition of the thumbs-up emoji: "used to express assent, approval or encouragement in digital communications, especially in western cultures", confirming that the thumbs-up emoji is an "action in an electronic form" that can be used to allow express acceptance as contemplated under the Canadian Electronic Information and Documents Act 2000. Justice Keene dismissed the concerns raised by the defence that accepting the thumbs up emoji as a sign of agreement would "open the flood gates" to new interpretations of other emojis, such as the 'fist bump' and 'handshake'. Significantly, the Court held, "I agree this case is novel (at least in Skatchewan), but nevertheless this Court cannot (nor should it) attempt to stem the tide of technology and common usage." Ultimately the Court found in favour of SWT, holding that there was a valid contract between the parties and that the defendant breached by failing to deliver the flax. Keene J made a judgment against ALC for damages in the amount of $82,200.21 payable to SWT plus interest.   What does this mean for Australia? This is a Canadian decision meaning that it is not precedent in Australia. However, an Australian court is well within its rights to consider this judgment when dealing with matters that come before it with similar circumstances. This judgment is a reminder that the common law of contract has and will continue to evolve to meet the everchanging realities and challenges of our day-to-day lives. As time has progressed, we have seen the courts transition from sole acceptance of the traditional "wet ink" signature, to electronic signatures. Electronic signatures are legally recognised in Australia and are provided for by the Electronic Transactions Act 1999 and the Electronic Transactions Regulations 2020. Companies are also now able to execute certain documents via electronic means under s 127 of the Corporations Act. We have also seen the rise of electronic platforms such as "DocuSign" used in commercial relationships to facilitate the efficient signing of contracts. Furthermore, this case highlights how courts will interpret the element of "intention" when determining whether a valid contract has been formed, confirming the long-standing principle that it is to be assessed objectively from the perspective of a reasonable and objective bystander who is aware of all the relevant facts. Overall, this is an interesting development for parties engaging in commerce via electronic means and an important reminder to all to be conscious of the fact that contracts have the potential to be agreed to by use of an emoji in today's digital age.

Published by Foez Dewan
29 August, 2023
Government

Venues NSW ats Kerri Kane: Venues NSW successful in overturning a District Court decision

The McCabes Government team are pleased to have assisted Venues NSW in successfully overturning a District Court decision holding it liable in negligence for injuries sustained by a patron who slipped and fell down a set of steps at a sports stadium; Venues NSW v Kane [2023] NSWCA 192 Principles The NSW Court of Appeal has reaffirmed the principles regarding the interpretation of the matters to be considered under sections5B of the Civil Liability Act 2002 (NSW). There is no obligation in negligence for an occupier to ensure that handrails are applied to all sets of steps in its premises. An occupier will not automatically be liable in negligence if its premises are not compliant with the Building Code of Australia (BCA). Background The plaintiff commenced proceedings in the District Court of NSW against Venues NSW (VNSW) alleging she suffered injuries when she fell down a set of steps at McDonald Jones Stadium in Newcastle on 6 July 2019. The plaintiff attended the Stadium with her husband and friend to watch an NRL rugby league match. It was raining heavily on the day. The plaintiff alleged she slipped and fell while descending a stepped aisle which comprised of concrete steps between rows of seating. The plaintiff sued VNSW in negligence alleging the stepped aisle constituted a "stairwell" under the BCA and therefore ought to have had a handrail. The plaintiff also alleged that the chamfered edge of the steps exceeded the allowed tolerance of 5mm. The Decision at Trial In finding in favour of the plaintiff, Norton DCJ found that: the steps constituted a "stairwell" and therefore were in breach of the BCA due to the absence of a handrail and the presence of a chamfered edge exceeding 5mm in length. even if handrails were not required, the use of them would have been good and reasonable practice given the stadium was open during periods of darkness, inclement weather, and used by a persons of varying levels of physical agility. VNSW ought to have arranged a risk assessment of the entire stadium, particularly the areas which provided access along stepped surfaces. installation of a handrail (or building stairs with the required chamfered edge) would not impose a serious burden on VNSW, even if required on other similar steps. Issues on Appeal VNSW appealed the decision of Norton DCJ. The primary challenge was to the trial judge's finding that VNSW was in breach of its duty of care in failing to install a handrail. In addition, VNSW challenged the findings that the steps met the definition of a 'stairwell' under the BCA as well as the trial judge's assessment of damages. Decision on Appeal The Court of Appeal found that primary judge's finding of breach of duty on the part of VNSW could not stand for multiple reasons, including that it proceeded on an erroneous construction of s5B of the Civil Liability Act 2002 and the obvious nature of the danger presented by the steps. As to the determination of breach of duty, the Court stressed that the trial judge was wrong to proceed on the basis that the Court simply has regard to each of the seven matters raised in ss 5B and 5C of the CLA and then express a conclusion as to breach. Instead, the Court emphasised that s 5B(1)(c) is a gateway, such that a plaintiff who fails to satisfy that provision cannot succeed, with the matters raised in s 5B(2) being mandatory considerations to be borne in mind when determining s 5B(1)(c). Ultimately, regarding the primary question of breach of duty, the Court found that: The stadium contained hazards which were utterly familiar and obvious to any spectator, namely, steps which needed to be navigated to get to and to leave from the tiered seating. While the trial judge considered the mandatory requirements required by s5B(2) of the CLA, those matters are not exhaustive and the trial judge failed to pay proper to attention to the fact that: the stadium had been certified as BCA compliant eight years before the incident; there was no evidence of previous falls resulting in injury despite the stairs being used by millions of spectators over the previous eight years; and the horizontal surfaces of the steps were highly slip resistant when wet. In light of the above, the Court of Appeal did not accept a reasonable person in the position of VNSW would not have installed a handrail along the stepped aisle. The burden of taking the complained of precautions includes to address similar risks of harm throughout the stadium, i.e. installing handrails on the other stepped aisles. This was a mandatory consideration under s5C(a) which was not properly taken into account. As to the question of BCA compliance, the Court of Appeal did not consider it necessary to make a firm conclusion of this issue given it did not find a breach of duty.  The Court did however indicated it did not consider the stepped aisle would constitute a "stairway" under the BCA. The Court of Appeal also found that there was nothing in the trial judge's reasons explicitly connecting the risk assessment she considered VNSW ought to have carried out, with the installation of handrails on any of the aisles in the stadium and therefore could not lead to any findings regarding breach or causation. As to quantum, the Court of Appeal accepted that the trial judge erred in awarding the plaintiff a "buffer" of $10,000 for past economic loss in circumstances where there was no evidence of any loss of income. The Court of Appeal set aside the orders of the District Court and entered judgment for VNSW with costs. Why this case is important? The case confirms there is no obligation in negligence for owners and operators of public or private venues in NSW to have a handrail on every set of steps. It is also a welcome affirmation of the principles surrounding the assessment of breach of duty under s 5B and s 5C of the CLA, particularly in assessing whether precautions are required to be taken in response to hazards which are familiar and obvious to a reasonable person.

Published by Leighton Hawkes
18 August, 2023
Litigation and Dispute Resolution

Expert evidence – The letter of instruction and involvement of lawyers

The recent decision in New Aim Pty Ltd v Leung [2023] FCAFC 67 (New Aim) has provided some useful guidance in relation to briefing experts in litigation.

Published by Justin Pennay
10 August, 2023